Brightline shaves almost a year from Florida rail project using precast tunnel system

3 min read

Table of Contents

Dive Brief:

  • The $2.seven billion, one hundred seventy-mile Brightline significant-velocity rail extension from West Palm Beach, Florida, to Orlando Worldwide Airport (OIA) will see the construction of a train tunnel in two months as a substitute of pretty much a person 12 months thanks to an impressive box-jack system advised by standard contractor Granite Building. This is the 1st time the box-jack system will be utilized for a train job exterior of the Northeast United States.
  • The developer of the box-jacking system, Italian corporation Petrucco, is using specific hydraulic jacks to press two precast concrete containers — one 146 toes extensive and the other 126 toes extensive and the two with 42-foot-extensive sidewalls — under a roadway east of the airport when an excavator digs out a path from within the box and from the opposite aspect. Just about every box weighs much more than three,000 tons, and the installation will choose a 40-human being crew doing work twelve-hour shifts close to the clock. 
  • Rail officers also strategy on using the box-jack system upcoming 12 months to develop a 2nd train tunnel underpass together the South Florida-to-OIA route in Cocoa, Florida, preventing shutting down website traffic for pretty much a 12 months in that location as nicely. 

Dive Perception:

Normally utilized in Europe for rail construction, the box-jacking technique was 1st utilized in the U.S. earlier this 12 months on the Extensive Island Railroad expansion job in New York City. In this job, similar precast concrete containers ended up put in below roadways doing away with the have to have for at-quality railroad crossings. 

Richard Brown, job supervisor for Granite, which solid the containers on web-site, told Building Dive that standard tunneling wasn’t an possibility on the Florida job since of the current grades of the roadway and the proposed monitor grades. In addition, regular construction procedures would have developed an close to 10-thirty day period detour for motorists, Brown mentioned, as opposed to the two-7 days detour that is now planned.

Beyond the Brightline job, Brown mentioned Granite will seem at box-jacking on potential work.

Granite’s $557 million part of the job is the 37-mile, Zone three part that operates from Cocoa to OIA, in accordance to Brightline spokesperson Katie Mitzner. Other contractors on the task involve:

  • Hubbard Building and Wharton-Smith Inc., which will conduct web-site preparing and creating on about 70 acres south of OIA, are the contracting workforce for Zone 1.
  • The Middlesex Company will handle web-site and infrastructure work in Zone 2, which stretches three miles by way of the airport. 
  • HSR Contractors, a joint venture in between Herzog, Stacy & Witbeck and RailWorks, will enhance close to one hundred thirty miles of current monitor in Zone 4. This improvement from Course IV to Course V monitor will let trains to journey up to a hundred and ten miles for every hour.

Very last thirty day period, Mitzner advised Building Dive that much more than 750 employees are currently manning the expansion and that the corporation expects to incorporate much more in the months forward. 

Get the job done on the expansion’s bridges and one hundred fifty five at-quality crossings is also underway. At the airport, contractors have laid rail and have damaged ground on a 109,000-sq.-foot car maintenance facility. 