Enbridge ordered to pay $3.3M for construction mistake on Line 3 replacement project

Dive Temporary: 

  • The Minnesota Office of Pure Methods has requested Enbridge Vitality Associates to shell out $3.32 million for failure to abide by environmental regulations all through development of a part of the company’s $2.9 billion Line 3 oil pipeline alternative task previously this year. 
  • Enbridge started perform at the Clearbrook, Minnesota, site early this year but did not adhere to the building programs it experienced delivered to the division, according to a Sept. 16 assertion from the DNR. The options termed for the use of standard trench development methods at a depth of 8 to 10 ft. The enterprise instead produced the trench at a depth of approximately 18 ft with sheet piling mounted to a depth of 28 toes. 
  • This deviation led to a breach of the confining layer of an artesian aquifer, resulting in an uncontrolled move of groundwater into the trench. Enbridge failed to notify DNR of the groundwater predicament, the statement reported. 

Dive Insight:

The fines consist of a restoration purchase requiring $300,000 in first mitigation cash to pay for the loss of groundwater methods, $250,000 for DNR monitoring of wetlands in the vicinity of the space of the aquifer breach and a $20,000 administrative penalty get, the utmost allowed underneath condition law. The DNR has also purchased Enbridge to area $2.75 million in escrow for restoration and mitigation of any damage to the special sort of wetlands acknowledged as calcareous fen wetlands, which rely on an upwelling of mineral-wealthy groundwater to thrive. 

The Line 3 undertaking is changing a 1,097-mile-extensive crude oil pipeline that runs from Edmonton, Canada, to Excellent, Wisconsin. 

Enbridge is also demanded to put into action a restoration strategy to stop the unauthorized groundwater flow inside of 30 times. The buy involves the organization to carry out more groundwater and internet site monitoring and report the effects, and also to build a management prepare. Also, to make sure that violations have not occurred in other places, the DNR is requiring Enbridge to fund a re-inspection of any and all places along the route where construction depths deviated from strategies.

The DNR has also referred the subject to the Clearwater County Lawyer for criminal prosecution beneath a statute that will make it a criminal offense to proper “waters of the condition without the need of previously obtaining a allow from the commissioner.” 

An Enbridge spokesperson told Building Dive that the organization is examining the DNR buy. 

“Enbridge has been doing work with the DNR given that June to supply the required web page info and acceptance of a corrective action approach which is at this time staying applied,” communications expert Juli Kellner reported in an electronic mail. “We share a sturdy motivation to secure Minnesota waters and the setting and we are committed to restoration.  We will go on to do the job closely with the company on the resolution of this subject.”